Road Closure - S. University

Back to Blog Posts

Happy Construction Cone

Published: Wed, 01/09/2019 - 10:20 AM

Related to

Notice of Temporary Traffic Control Plan: South University Avenue between East University Avenue and Church Street,

7 a.m. Monday, Jan. 14–Wednesday, Jan. 23 at 5 p.m.

Location and Limits of Affected Area:

South University Avenue between East University Avenue and Church Street.

Description of Work:

Wolverine Building Group will be closing South University Avenue to through traffic in both directions in order to disassemble a crane.

For the safety of the traveling public and work crews, the contractor will implement the following traffic control plan. 

Temporary Construction Traffic Control Plan:

Eastbound South University Avenue will be detoured to southbound East University Avenue to eastbound Hill Street to northbound Church Street.

Westbound South University Avenue will be detoured to southbound Church Street to westbound Hill Street to northbound East University Avenue. Pedestrian access will be maintained on the south side of South University, and pedestrian traffic on the north side of South University Avenue will be detoured to the south side.

The contractor will be shutting down the intersection of East University and South University for a few hours at a time to complete the disassembly of the crane. The contractor will be detouring traffic using flaggers at the intersections of both Hill Street at East University Avenue and at South University Avenue and Tappan Avenue during those brief times.